5 Common Microsoft Project Mistakes to Avoid (And How to Fix Them)

In this blog post, I’m going to walk you through the 5 most common Microsoft Project mistakes I see project managers make every week, along with the exact steps to fix each one. Over my nearly 30 years teaching and consulting on Microsoft Project, I have audited hundreds of schedules that stopped calculating properly, showed impossible resource overallocations, or hid schedule slippage simply because of these five avoidable habits.

Companion Articles in This Tasks, Dependencies & Critical Path Series: Explore these connected tutorials in the same topic area to build your skills step by step:

5 Common Microsoft Project Mistakes to Avoid (And How to Fix Them)

YouTubeWatch the Step-by-Step Video

Prefer to follow along visually? This video demonstrates the exact steps you’ll learn below using Microsoft Project Desktop.

At a Glance: 5 Common Microsoft Project Mistakes & Their Fixes:

  • Mistake #1 (Typing Start & Finish Dates): Manually typing dates sets rigid task constraints. Fix: Enter Duration and Predecessors so Microsoft Project calculates all dates dynamically.
  • Mistake #2 (Using Manually Scheduled Tasks): Manually Scheduled tasks ignore dependencies and calendar changes. Fix: Switch all tasks to Auto Scheduled.
  • Mistake #3 (Linking Summary Tasks): Putting dependencies on Summary Tasks can lead to circular relationships and will often hide the Critical Path. Fix: Link detail tasks and milestones only.
  • Mistake #4 (Assigning Resources to Summary Tasks): Doing this causes Microsoft Project to multiply the Work and Cost, and triggers false resource overallocations. Fix: Assign resources strictly to detailed tasks.
  • Mistake #5 (Tracking Progress Without a Baseline): Leaves all Variance fields with incorrect values. Fix: Always save a Baseline before entering actual progress.

Need hands-on help with your schedule? Explore my $399 Microsoft Project Desktop Course, Project Server Training, or book 1-on-1 Private Training & Consulting.

Mistake #1: Why Should You Never Type Start and Finish Dates Manually?

When beginners transition from Microsoft Excel to Microsoft Project, their first instinct is to type the Task Name and then type dates directly into the Start and Finish columns.

Believe me, you won’t like the results if you type Start and Finish dates into your schedule! Whenever you type or pick a date in the Start column, Microsoft Project quietly applies a Start No Earlier Than (SNET) task constraint (indicated by a calendar icon in the Indicators column) and does not ask your permission to do so. If a predecessor task actually starts early, your constrained task refuses to pull in earlier!

How to Fix Mistake #1:

  1. Never type dates in the Start or Finish columns (except when entering actual dates in Actual Start or Actual Finish during tracking).
  2. Instead, enter the Duration for each task and link tasks using the Predecessors column so Microsoft Project’s scheduling engine calculates all Start and Finish dates automatically.
  3. To remove accidental constraints on existing tasks:
    1. Select each constrained task row and double-click to open the Task Information dialog.
    2. Click the Advanced tab at the top of the dialog.
    3. Click the Constraint type pick list button, select As Soon As Possible, and click OK.

Mistake #2: Why Are Manually Scheduled Tasks Breaking Your Schedule Logic?

By default in a brand-new installation of Microsoft Project, the Task Mode for new tasks is set to Manually Scheduled (represented by a pushpin icon in the Task Mode column). Manually scheduled tasks act like static spreadsheet rows: if a predecessor slips by two weeks, a Manually Scheduled successor task will not move automatically!

How to Fix Mistake #2:

  1. To convert existing tasks in your schedule, select all rows, click the Task ribbon tab, and click the Auto Schedule button in the Tasks section.
  2. To make sure every future project defaults to Auto Scheduled tasks:
    1. Click the New Tasks : Manually Scheduled status bar item in the lower-left corner of the Microsoft Project window and choose Auto Scheduled, OR
    2. Open File -> Options -> Schedule, scroll to Scheduling options for this project, click the All New Projects pick list, and set New tasks created to Auto Scheduled.

Mistake #3: Why Should You Avoid Putting Dependencies on Summary Tasks?

It is very tempting to link Phase 1 (Row 1) directly to Phase 2 (Row 10) in the Predecessors column. However, PMI scheduling standards and Microsoft Project best practices strongly advise against linking Summary Tasks:

  • Summary Task dependencies obscure the real task-to-task handoffs driving your Critical Path.
  • Combining Summary Task links with detail task links is the #1 cause of the dreaded “Circular relationship” error message in Microsoft Project. Circular reference errors are really difficult to troubleshoot and resolve, so it is best to completely avoid them!

How to Fix Mistake #3:

  1. Remove all Predecessor and Successor values from every Summary Task row.
  2. Place a Milestone at the end of each phase, such as a milestone named Design Complete for the Design phase.
  3. Link that Phase 1 Milestone as the Predecessor to the first detail task in Phase 2.

Mistake #4: Why Does Assigning Resources to Summary Tasks Cause Overallocation?

What happens if you assign a Project Manager or Lead Engineer to a Summary Task and also assign them to the detail tasks indented beneath that Summary Task? Microsoft Project adds all the assignments together, instantly creating a false resource overallocation (displaying the red burning man icon in the Indicators column) and inflating your project labor budget tremendously!

How to Fix Mistake #4:

  1. Never assign Work, Material, or Cost resources to a Summary Task row.
  2. Assign resources exclusively to detailed tasks at the lowest level of your Work Breakdown Structure.
  3. If you need to track a Project Manager’s ongoing level-of-effort oversight across a phase, create a dedicated detail task (often called a Hammock Task or Level of Effort task) inside that phase and assign the Project Manager there.

Mistake #5: Why Is Tracking Progress Without Saving a Baseline a Disaster?

Suppose your project is halfway done, and your executive sponsor asks, “How many days behind our original schedule are we, and how much over budget?” If you started typing % Complete or actuals without first saving a Baseline, every single Baseline column in your schedule reads either 0 or NA, and all Variance columns (Finish Variance, Work Variance, Cost Variance) display incorrect variance information!

How to Fix Mistake #5:

  1. The moment your initial project schedule is reviewed and approved (and before you enter a single hour of actual progress), click the Project ribbon tab.
  2. In the Schedule section, click the Set Baseline pick list button and choose Set Baseline.
  3. In the Set Baseline dialog:
    1. Leave Set baseline selected with Baseline (the primary baseline) chosen in the dropdown list.
    2. Leave Entire project selected under For.
    3. Click OK.

Frequently Asked Questions

How can I quickly check if my schedule has any of these 5 mistakes?

You can download my Free Microsoft Project Quality Filters, which automatically flag constrained tasks, unlinked tasks, resources assigned to Summary Tasks, and dependencies on Summary Tasks in seconds!

Is there ever a valid reason to use a Task Constraint in Microsoft Project?

Yes, but only when there is a real-world restriction outside the project team’s control (such as a vendor contract delivery date or an outdoor construction window that cannot start before April 1). Even then, you may prefer using a Deadline date whenever you want an alert without locking your schedule logic.

What if I already started tracking progress and forgot to save a Baseline?

Save a Baseline immediately (Project -> Set Baseline -> Set Baseline). While it will capture current dates for tasks already completed, it will lock in your baseline for all remaining in-progress and future tasks from today forward.

Does Planner Premium (formerly named Project for the Web) have Manually Scheduled tasks?

No! In Planner Premium (formerly named Project for the Web), all tasks are automatically scheduled based on dependencies and duration, though Microsoft Project Desktop still gives you the choice between Manually Scheduled and Auto Scheduled.


Ready to master Microsoft Project? If you found this article helpful, check out my free tutorials on my YouTube channel, download my Free Microsoft Project Quality Filters, or explore my structured, expert-led training courses and 1-on-1 coaching at dalehowardmvp.com.