In this blog post, I’m going to show you how to perform Rolling Wave Planning in Microsoft Project without corrupting your historical baseline or losing schedule variance. On long or complex projects, you rarely know every single detail task for Phase 3 and Phase 4 on Day 1, for example. Instead, you plan Phase 1 and Phase 2 in detail, create high-level Planning Packages for future phases, and decompose those Planning Packages into detailed tasks as each phase approaches!
Companion Articles in This Baselines, Variance & Progress Tracking Series: Explore these connected tutorials in the same topic area to build your skills step by step:
- Current Article (You Are Here): How to Do Rolling Wave Planning in Microsoft Project Without Losing Historical Variance
- Companion Tutorial: Why Should You Save a Baseline in Microsoft Project?
- Companion Tutorial: How to Enter Task Progress in Microsoft Project (Step-by-Step)
- Companion Tutorial: Understanding Finish Variance and Other Variance Fields in Microsoft Project
- Full Topic Hub: Browse All Baselines, Variance & Progress Tutorials →
At a Glance: Rolling Wave Planning in Microsoft Project:
- Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and Project Online Desktop Client).
- Step 1 (Initial Setup): Plan near-term phases in full detail, enter single-row Planning Package placeholder tasks for future phases (with estimated Duration, Work, or Cost), and save
Baseline(Baseline 0) across the entire project. - Step 2 (Expand a Planning Package): When a future phase approaches, insert your new detail tasks right below the Planning Package row, indent them (Task -> Indent Task) so the Planning Package becomes a Summary Task, and remove all Predecessors, Resources, and Fixed Costs from the new Summary Task row.
- Step 3 (Update the Baseline Safely): Copy your original
BaselineintoBaseline 1for historical archive, then saveBaselinefor Selected tasks (checking To all summary tasks under Roll up baselines) so Phases 1 and 2 keep their original baseline untouched!
Need hands-on help with your schedule? Explore my $399 Microsoft Project Desktop Course, Project Server Training, or book 1-on-1 Private Training & Consulting.
What Is Rolling Wave Planning (And How Do Planning Packages Work)?
According to PMI’s PMBOK Guide, Rolling Wave Planning is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level inside Planning Packages.
In Microsoft Project, here is an example of how your schedule might look at the start of the project:
- Phase 1 & Phase 2 (Near-Term Phases): Fully decomposed into detail tasks, linked with task dependencies, and loaded with assigned resources.
- Phase 3 & Phase 4 (Future Planning Packages): Entered as single un-indented placeholder tasks (for example,
Phase 3 - Build & Integrationwith a Duration value of40d) linked after Phase 2, with high-level estimated work or budget assigned so your initial project finish date and budget are complete when you save your initial Baseline.
Step 1: How Do I Expand a Planning Package into Detail Tasks When the Phase Approaches?
Suppose your team is finishing up Phase 2, and you now know the exact detail tasks required for Phase 3. Follow these steps carefully to convert the Phase 3 Planning Package into a proper Phase Summary Task:
- In the Gantt Chart view, right-click the Row Header (row ID number) directly below the Phase 3 Planning Package row and click the Insert Task item on the shortcut menu to insert blank rows for your new Phase 3 detail tasks.
- Type the Task Names and Durations for all of the new Phase 3 detail tasks.
- Select the newly inserted Phase 3 detail task rows, click the Task ribbon tab, and click the Indent Task button in the Schedule section.
- CRITICAL CLEAN-UP STEP: Because indenting the detail tasks turned the Phase 3 Planning Package row into a Summary Task, you must immediately remove the old Planning Package data from the Phase 3 Summary Task row:
- Delete the Predecessors and Successors values on the Phase 3 Summary Task row.
- Delete any Resource Names or Fixed Cost values that were assigned to the Phase 3 Summary Task row.
- Link your new Phase 3 detail tasks into the dependency chain (connecting the end of Phase 2 to the first detail task of Phase 3, and connecting the final milestone of Phase 3 to Phase 4), and assign resources to the new Phase 3 detail tasks!
Step 2: How Do I Archive My Original Baseline Before Updating Phase 3?
Before you baseline the newly added Phase 3 detail tasks, always preserve a complete snapshot of your previous baseline in one of Microsoft Project’s 10 extra baselines (Baseline 1 through Baseline 10):
- Click the Project ribbon tab, click the Set Baseline pick list button in the Schedule section, and choose Set Baseline.
- In the Set Baseline dialog:
- Select the Set interim plan radio button.
- In the Copy pick list, leave Baseline selected.
- In the Into pick list, select
Baseline 1(or the next unused archive baseline number). - Leave Entire project selected and click OK.
Now your original Planning Package baseline is permanently preserved in Baseline 1!
Step 3: How Do I Baseline Only the New Detail Tasks and Roll Up to Summary Tasks?
Finally, let’s baseline your new Phase 3 detail tasks inside the primary Baseline (which drives all Variance calculations in Microsoft Project) without overwriting the historical baseline on Phases 1 and 2:
- In the Gantt Chart screen, select only the newly added detail task rows inside Phase 3 (plus any downstream Planning Packages whose planned dates shifted as a result of detailing Phase 3).
- Click the Project ribbon tab, click the Set Baseline pick list button, and choose Set Baseline.
- In the Set Baseline dialog:
- Leave the Set baseline radio button selected with Baseline chosen in the dropdown list.
- Under For, select the Selected tasks radio button.
- Under Roll up baselines, check the checkbox labeled To all summary tasks (and leave From subtasks into selected summary task(s) unchecked).
- Click OK, and click Yes when Microsoft Project asks you to confirm overwriting the baseline for the selected tasks.
Why is checking To all summary tasks so important? Because it forces Microsoft Project to recalculate the rolled-up Baseline Duration, Baseline Start, Baseline Finish, Baseline Work, and Baseline Cost on both the Phase 3 Summary Task and Row 0 (the Project Summary Task), while leaving every single task in Phase 1 and Phase 2 completely untouched!
Frequently Asked Questions
What happens if I forget to check “To all summary tasks” when baselining selected tasks?
If you baseline selected detail tasks without checking To all summary tasks, the detail tasks get their new Baseline values, but the parent Phase Summary Task and Row 0 (the Project Summary Task) keep their old Planning Package baseline numbers! That causes your detail task baselines and your Summary Task baselines to stop adding up.
Why must I remove Resources and Predecessors from the Planning Package row when it becomes a Summary Task?
As I cover in my guide on the task constraints and Summary Tasks, leaving resources on a Summary Task greatly increases the work and cost on top of your new detail tasks, and leaving Predecessors/Successors on a Summary Task can trigger circular dependency errors when you link the subtasks underneath it.
How many times can I repeat this Rolling Wave baseline process on a project?
Microsoft Project gives you 11 total baselines (Baseline plus Baseline 1 through Baseline 10). That means you can archive up to 10 separate Rolling Wave baseline snapshots (Baseline 1 for Wave 1, Baseline 2 for Wave 2, and so on) while always keeping your active baseline in Baseline!
Should I ever re-baseline the “Entire project” during Rolling Wave Planning?
No! If you select Entire project when setting Baseline mid-project, Microsoft Project overwrites the original baseline on all of your completed and in-progress tasks in Phase 1 and Phase 2, wiping out your historical variance and making it look like past delays never happened. Always use Selected tasks with To all summary tasks checked!
Ready to master Microsoft Project? If you found this article helpful, check out my free tutorials on my YouTube channel, download my Free Microsoft Project Quality Filters, or explore my structured, expert-led training courses and 1-on-1 coaching at dalehowardmvp.com.