In this blog post, I’m going to show you how to budget for and track actual non-labor expense costs in Microsoft Project using Expense Cost resources. While most project managers know how to track labor hours for people (Work resources), many get stuck when an invoice for travel, airfare, lodging, vendor permits, or software licenses arrives and costs more (or less) than originally budgeted.
Companion Articles in This Resources, Assignments & Cost Management Series: Explore these connected tutorials in the same topic area to build your skills step by step:
- Current Article (You Are Here): How to Track Actual Expense Costs in Microsoft Project Using Cost Resources
- Companion Tutorial: How to Assign Resources to Tasks in Microsoft Project
- Companion Tutorial: Effort-Driven Scheduling in Microsoft Project Explained
- Companion Tutorial: How to Enter and Track Fixed Costs in Microsoft Project
- Full Topic Hub: Browse All Resources & Cost Management Tutorials →
At a Glance: Tracking Expense Costs in Microsoft Project:
- Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and Project Online Desktop Client).
- Step 1: Display the Resource Sheet view and create an Expense Cost resource for each of your expense categories (such as
Travel Expenses,Lodging, orPermit Fees) with the Type column set toCost. - Step 2: Assign the Expense Cost resource to a task, enter the budgeted dollar amount in the Cost field of the Assign Resources dialog, and save your project Baseline.
- Step 3: During the Execution stage of the project, display the Task Usage view, apply the Cost table (View -> Tables -> Cost), enter the real invoice amount in the
Actualcolumn for the Expense Cost resource assignment row, and setRemainingto$0.00.
Need hands-on help with your schedule? Explore my $399 Microsoft Project Desktop Course, Project Server Training, or book 1-on-1 Private Training & Consulting.
Why Should You Use Cost Resources Instead of the Fixed Cost Column?
In Microsoft Project, have you ever noticed a column called Fixed Cost in the Cost table? While you can type a single lump-sum dollar amount into the Fixed Cost column on a task row, doing so has two major drawbacks:
- No Expense Breakdown: If a single task includes airfare, hotel lodging, and meals, Fixed Cost lumps all three together into one anonymous number with no accounting category.
- Better Reporting with Cost Resources: When you create dedicated Cost Resources (such as
Airfare,Hotel,Equipment Rental, orVendor Permits), you can assign multiple expense types to the same task, track each invoice separately, and filter or group your Cash Flow reports by expense category!
Step 1: How Do I Create Cost Resources on the Resource Sheet?
First, let’s set up your non-labor expense items in the Resource Sheet view:
- Click the View ribbon tab and click the Resource Sheet button in the Resource Views section.
- In the Resource Name column, type the name of your expense category (for example,
TravelExpense orPermit Fees). - In the Type column on that row, click the pick list button and change the resource type from
WorktoCost.
Notice that when you select Cost as the Resource Type, Microsoft Project automatically locks the Max. Units, Std. Rate, and Ovt. Rate fields. That is because a Cost Resource does not work hours and never causes resource overallocation: you assign its dollar value directly when you assign it to a task!
Step 2: How Do I Budget Expense Costs and Save the Baseline?
Next, let’s assign your Cost Resource to a task and enter its planned budget:
- Switch back to the Gantt Chart view (View -> Gantt Chart) and select the task that will incur the expense.
- Click the Resource ribbon tab and click the Assign Resources button.
- In the Assign Resources dialog:
- Select your Cost Resource (for example,
Travel). - Click inside the Cost column on that resource row, type the budgeted dollar amount (for example,
$2,500), and press Enter (or click Assign). - Click Close.
- Select your Cost Resource (for example,
- Once all of your initial labor and expense budgets are entered, save your Baseline (Project -> Set Baseline -> Set Baseline -> OK) so Microsoft Project locks
$2,500intoBaseline Cost.
Step 3: How Do I Enter Actual Expense Invoices in the Task Usage View?
Now let’s record the actual invoice amount when the bill comes in (for example, suppose your budgeted $2,500 for travel which actually cost $2,850):
- Click the View ribbon tab and click Task Usage in the Task Views section.
- Still on the View ribbon tab, click the Tables pick list button in the Data section and select Cost.
- In the Cost table on the left side of the Task Usage screen, locate your task row and look at the indented Cost Resource assignment row directly beneath it (for example,
TravelExpense):- Notice that
Baselinedisplays$2,500.00andRemainingdisplays$2,500.00. - Click in the
Actual(Actual Cost) column on theTravelassignment row, type$2,850, and press Enter. - If no further travel invoices will arrive for this task, click in the
Remaining(Remaining Cost) column on theTravelassignment row, type$0, and press Enter.
- Notice that
Immediately, Microsoft Project updates Total Cost to $2,850.00, compares it against your $2,500.00 Baseline, and calculates a Variance (Cost Variance) of $350.00, rolling that exact variance up to Row 0 (the Project Summary Task)!
Frequently Asked Questions
Why did Total Cost jump to $5,350 when I typed $2,850 into Actual Cost?
Wait a minute! Why did Microsoft Project add the two numbers together? If you type an Actual Cost that is higher than your original budget while the task is still in progress, or if you forget to zero out Remaining Cost, double-check the Remaining column on the assignment row. Setting Remaining to $0.00 once all invoices are received ensures Total Cost = Actual Cost + Remaining Cost = $2,850 + $0 = $2,850.
What if an invoice comes in under budget (for example, $2,100 instead of $2,500)?
When you type $2,100 into the Actual column for a $2,500 budgeted Cost Resource, Microsoft Project automatically assumes you still have $400 left to spend and leaves Remaining at $400.00! If that $2,100 invoice is final, simply type $0 into the Remaining column so Total Cost drops to $2,100 and Variance shows -$400.00 (under budget).
Can I enter timephased expense costs by month or week?
Yes! In the Task Usage view, look at the timescaled grid on the right side of the screen. Right-click inside the yellow/white grid area and click the Actual Cost item on the shortcut menu to display the Act. Cost row alongside Cost. You can then type exact invoice dollar amounts into the specific week or month they were incurred.
Do Cost Resources affect task Duration or Work hours?
Never. Cost Resources have zero impact on task Duration, Work, or Effort Driven scheduling. They exist purely to track budgeted, actual, and remaining monetary expenses.