How to Display a High-Level Executive Schedule in Microsoft Project

In this blog post, I’m going to show you two fast, reliable ways to display a high-level executive schedule in Microsoft Project. When you walk into a steering committee meeting with a 400-line schedule, executives don’t want to scroll through hundreds of granular work packages; they want to see your high-level Phases, Deliverables, and key Milestones on a single screen.

Companion Articles in This Views, Tables, Filters & Formatting Series: Explore these connected tutorials in the same topic area to build your skills step by step:

How to Display a High-Level Executive Schedule in Microsoft Project

YouTubeWatch the Step-by-Step Video

Prefer to follow along visually? This video demonstrates the exact steps you’ll learn below using Microsoft Project Desktop.

At a Glance: High-Level Schedule Display in Microsoft Project:

  • Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and Project Online Desktop Client).
  • Method 1 (Collapse by Outline Level): Click View -> Outline and choose Outline Level 1 (for Phases) or Outline Level 2 (for Phases and Deliverables) to collapse all detail tasks simultaneously.
  • Method 2 (Show Summary Tasks + Milestones Together): Create a custom filter (View -> Filter -> More Filters -> New) where Summary equals Yes OR Milestone equals Yes so executives see every Phase and every Milestone on one screen!

Need hands-on help with your schedule? Explore my $399 Microsoft Project Desktop Course, Project Server Training, or book 1-on-1 Private Training & Consulting.

Method 1: How Do I Collapse the Schedule by Outline Level?

In a properly structured Work Breakdown Structure (WBS), your Summary Tasks sit at specific indentation levels: Outline Level 1 for top-level Phases, Outline Level 2 for major Deliverables, and Outline Level 3 for sub-Deliverables.

Instead of clicking the tiny expand/collapse triangles next to each Summary Task one by one, use the Outline button to collapse the entire schedule in two clicks:

  1. With the Gantt Chart view applied, click the View ribbon tab.
  2. In the Data section, click the Outline pick list button:
    1. Choose Outline Level 1 to display only Row 0 (the Project Summary Task) and your top-level Phases.
    2. Choose Outline Level 2 to expand one level deeper and show both Phases and major Deliverables.
    3. When your executive meeting is over, click the Outline pick list button and choose All Subtasks to expand every row back out!

Why Isn’t Collapsing to Outline Level 1 Enough When Executives Want to See Milestones?

Wait a minute! What happens when your project sponsor says, “Dale, I want to see all the high-level Phases AND all the project Milestones, without any of the detail tasks”?

  • If you click View -> Outline -> Outline Level 1, any Milestone indented at Outline Level 2 or Level 3 gets hidden inside its collapsed Phase!
  • And if you click View -> Filter -> Milestones, Microsoft Project shows your Milestones and their parent Summary Tasks, but hides any Phase or Summary Task that doesn’t happen to contain a Milestone!

To show every Summary Task and every Milestone together while hiding all detail work packages, let’s build a simple 2-line custom filter.

Method 2: How Do I Create a Custom “Summary Tasks and Milestones” Filter?

Follow these steps once, and you will have a one-click executive view ready for every status meeting:

  1. Click the View ribbon tab, click the Filter pick list button in the Data section, and choose More Filters… at the bottom of the menu.
  2. In the More Filters dialog, click the New… button.
  3. In the Filter Definition dialog:
    1. In the Name box at the top, type Summary Tasks and Milestones.
    2. Check the Show in menu checkbox so this filter appears right on your main Filter dropdown menu.
    3. On Row 1 of the filter grid, select Summary in the Field Name column, select equals in the Test column, and select Yes in the Value(s) column.
    4. On Row 2 of the filter grid, select Or in the And/Or column, select Milestone in the Field Name column, select equals in the Test column, and select Yes in the Value(s) column.
    5. Click Save to close the Filter Definition dialog.
  4. Back in the More Filters dialog, click Apply.

Quick and easy, right? Now your Gantt Chart screen displays every single Phase/Summary Task and every single Milestone diamond across the entire project, with zero detail tasks cluttering the view!

Frequently Asked Questions

How do I share my custom “Summary Tasks and Milestones” filter with all future projects?

Use the Organizer to copy your new filter into your Global.mpt template! Click File -> Info -> Organizer, click the Filters tab at the top of the Organizer dialog, select Summary Tasks and Milestones on the right side (your current .mpp file), click the << Copy button to copy it into Global.mpt on the left, and click Close.

How do I return to my full project schedule after applying the filter?

Click the View ribbon tab, click the Filter pick list button in the Data section, and select No Filter (or press the keyboard shortcut F3).

How can I check which Outline Level each task is on?

Right-click any column header in the Gantt Chart task table, click the Insert Column item on the shortcut menu, and insert the Outline Level column. You will immediately see 0 for the Project Summary Task, 1 for Phases, 2 for Deliverables, and 3 for sub-Deliverables.

Can I combine this high-level view with the Timeline pane?

Absolutely! In fact, applying the Summary Tasks and Milestones filter first makes it super easy to select all visible rows, right-click, and click the Add to Timeline item on the shortcut menu to populate the Timeline view in seconds.


Ready to master Microsoft Project? If you found this article helpful, check out my free tutorials on my YouTube channel, download my Free Microsoft Project Quality Filters, or explore my structured, expert-led training courses and 1-on-1 coaching at dalehowardmvp.com.