In this blog post, I’m going to show you how to troubleshoot the four most common reasons task dates and durations suddenly move in Microsoft Project. Few things frustrate a project manager more than carefully setting up a task’s Duration, Start, and Finish dates, only to watch those dates or durations jump unexpectedly the moment you assign resources to the task!
Companion Articles in This Calendars, Holidays & Working Time Series: Explore these connected tutorials in the same topic area to build your skills step by step:
- Current Article (You Are Here): Why Are My Task Dates Moving in Microsoft Project? Troubleshooting Calendar and Resource Issues
- Companion Tutorial: How to Create a Weekend Work Calendar in Microsoft Project
- Companion Tutorial: How to Add Company Holidays to a Microsoft Project Calendar
- Companion Tutorial: How to Create a 6-Day Work Week in Microsoft Project
- Full Topic Hub: Browse All Calendars & Working Time Tutorials →
At a Glance: Why Task Dates Move in Microsoft Project (And How to Fix It):
- Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and Project Online Desktop Client).
- Important Diagnostic Step (Show Time of Day): Open File -> Options -> General and choose a Date format that displays the time of day (
1/28/09 12:33 PM) so hidden half-day shifts become visible immediately. - Cause #1 (Resource Vacation / PTO): A resource’s personal calendar has non-working exception days during the task window, pushing out the
Finishdate. - Cause #2 (Task Calendar vs. Resource Calendar Conflict): You applied a custom Task Calendar without checking Scheduling ignores resource calendars in the Task Information dialog.
- Cause #3 (Effort-Driven Duration Shrinkage): Adding a second resource after the initial assignment cuts the task
Durationin half unless you change the Task Type or use the Actions smart tag.
Need hands-on help with your schedule? Explore my $399 Microsoft Project Desktop Course, Project Server Training, or book 1-on-1 Private Training & Consulting.
Important Diagnostic Step: How Do I Turn On Time-of-Day Display in Microsoft Project?
Before you can diagnose why a task’s Start or Finish date moved by an extra calendar day, you need to see the exact hour and minute each task starts and finishes. Suppose a 1-day (8-hour) task starts on Monday at 1:00 PM: it won’t finish until Tuesday at 12:00 PM, which makes a 1-day task look like it spans two calendar dates!
Turn on the date-and-time format whenever you are troubleshooting schedule dates:
- Click the File tab and click Options at the bottom of the menu.
- In the Project Options dialog:
- Leave the General tab selected.
- In the Project view section, click the Date format pick list button.
- Select the first date format, which includes the time of day (
1/28/09 12:33 PM). - Click OK.
Cause #1: Did a Resource’s Personal Vacation Calendar Push Out the Task Dates?
Before any resources are assigned to a task, Microsoft Project schedules the task using the Project Calendar (usually Standard, Monday through Friday, 8:00 AM to 5:00 PM). However, the moment you assign a Work Resource to that task, the resource’s personal calendar takes over!
If Mickey has Thursday and Friday marked as non-working PTO exception days in the Change Working Time dialog, assigning Mickey to a 5-day task starting Monday forces Microsoft Project to push the task’s Finish date out to the following Tuesday! Even though the task Duration still reads 5d (40 hours of working time), the Gantt bar stretches across 7 working days to bridge around Mickey’s vacation.
How to Check & Fix:
- Click Project -> Change Working Time.
- In the For calendar pick list at the top of the Change Working Time dialog, select the assigned resource’s name and look at the Exceptions tab at the bottom to see if they have scheduled time off during that week.
Cause #2: Did a Custom Task Calendar Conflict with the Resource Calendar?
Suppose you create a custom Base calendar named Weekend Work Calendar so a critical cutover task can run on Saturday and Sunday. You apply that Task Calendar to the task, and the dates move cleanly onto the weekend. Then you assign Calvin to the task, and uh-oh! The task immediately jumps off the weekend and moves to Monday morning!
Why did that happen? Because by default, when both a Task Calendar and a Resource Calendar are present on the same task, Microsoft Project schedules work only during the common working hours shared by both calendars! Since Calvin’s calendar says Saturday and Sunday are non-working days, Microsoft Project refuses to schedule him on the weekend.
How to Fix It in the Task Information Dialog:
- Double-click the task row in the Gantt Chart view to open the Task Information dialog.
- In the Task Information dialog:
- Click the Advanced tab at the top of the dialog.
- Confirm your custom calendar is selected in the Calendar pick list button.
- Check the checkbox right next to it labeled Scheduling ignores resource calendars.
- Click OK.
Immediately, the task snaps right back onto the weekend!
Cause #3: Why Did My Task Duration Shrink in Half When I Added Another Resource?
What if your Start date stayed put, but your 10-day task suddenly shrank to a 5-day task (moving the Finish date a whole week earlier) when you assigned a second team member?
That happens when you add additional resources after the initial resource assignment on a task that uses Effort Driven scheduling (or when you change units on a Fixed Work task). Microsoft Project assumes that keeping total Work constant (80 hours) with two people instead of one cuts the Duration in half (5 days)!
How to Fix It:
- When you add a second resource and the Duration changes, click the small Actions smart tag triangle that appears next to the Resource Names cell and select Increase the amount of work, but keep the same duration.
- Alternatively, if you want task
Durationto stay locked whenever you add or remove resources, change the task’s Task Type toFixed Durationon the Advanced tab of the Task Information dialog before assigning resources!
Frequently Asked Questions
Why did a task’s Start Date move even though it has no Predecessors and no Resources?
Check the Indicators column on the far left of the task table! If you see a small calendar icon, someone manually typed a date or applied a Task Constraint (such as Start No Earlier Than). Also check whether the task is indented underneath a Summary Task that has a Predecessor or Constraint applied to the Summary Task row!
Why does a 5-day task start at 8:00 AM on Monday and finish at 8:00 AM the following Monday?
That happens when your Calendar working hours (Project -> Change Working Time -> Work Weeks -> Details) only allow 7.5 hours per day, while your Schedule options (File -> Options -> Schedule -> Hours per day) still define 1 day as 8 hours! Because 5 days * 8 hours = 40 hours, working 7.5 hours per day leaves 2.5 hours spilling over into the following Monday morning. Always make sure Hours per day matches your calendar’s daily working hours!
Does Resource Leveling move task dates automatically?
Only if you have Leveling calculations set to Automatic in Resource -> Leveling Options! Always keep Resource Leveling set to Manual (Resource -> Leveling Options -> Manual) so Microsoft Project never adds leveling delay to your tasks behind your back.