Fix Your Enterprise Global File

WARNING: This blog post article is specifically for people who are the application administrators for their organization’s Project Server instance. If you are only a project manager in your organization, you will not have the necessary permissions to complete the steps detailed below to Fix Your Enterprise Global File.

Are project managers in your organization seeing a warning dialog such as “There is a report named [Report Name] in this project which cannot be overwritten” whenever they try to open and check out an enterprise project? If so, fear not. This is the result of “pollution” in your Enterprise Global file – a common mistake made by rookie application administrators.

Remember that your Enterprise Global file should only contain enterprise objects, such as enterprise views and enterprise tables. “Pollution” consists of non-enterprise objects in the Enterprise Global, such as local views and local tables. In this guide, I’ll walk you through the steps to remove “pollution” from the Enterprise Global file, which will ensure a smooth experience for your project managers with their enterprise projects.

If you would rather watch a YouTube video on this subject, click here or click the thumbnail below.

Fix Your Enterprise Global File

Fix Your Enterprise Global File: Step by Step

If you are the application administrator of your organization’s Project Server instance, complete the following steps to Fix Your Enterprise Global File.

  1. Click the File tab to display the Backstage.
  2. Click the Info tab in the Backstage.
  3. Click the Organizer pick list button and select the Open Enterprise Global item in the menu.
  4. Click the File tab again.
  5. Click the Info tab again.
  6. Click the Organizer pick list button again and select the Organizer item in the menu.
  7. In the list of views on the right side of the Organizer dialog, select every non-enterprise view. This will include local views such as the Gantt Chart, Resource Sheet, and Task Usage views.
  8. With all non-enterprise views selected, click the Delete button.
  9. Confirm the deletion by clicking the Yes to All button.
  10. Click the Tables tab.
  11. In the list of Task tables on the right side of the Organizer dialog, select every non-enterprise table. This will include local tables such as the Entry and Usage tables.
  12. With all non-enterprise Task tables selected, click the Delete button.
  13. Confirm the deletion by clicking the Yes to All button.
  14. Click the Resource option in the upper-left corner of the dialog.
  15. In the list of Resource tables on the right side of the Organizer dialog, select every non-enterprise table. This will include local tables such as the Entry table.
  16. With all non-enterprise Resource tables selected, click the Delete button.
  17. Confirm the deletion by clicking the Yes to All button.
  18. Click the Close button to close the dialog.
  19. Save the changes to the Enterprise Global file.
  20. Close the Enterprise Global file, and be sure to check it in.
  21. Exit Microsoft Project completely, then launch the software again and connect to PWA.
  22. Send an email to all project managers, instructing them to exit Microsoft Project completely, and then to relaunch the software and connect again to PWA.

By completing the preceding steps, you’ll successfully clean up the “pollution” in your Enterprise Global file, ensuring that it only contains only enterprise objects, such as enterprise views, tables, filters, and groups. If you have questions, please add them in the “Leave a Reply” section below. Or if you watched the video, add your questions or comments there. Please subscribe to my YouTube channel and leave “Likes” if you like the videos.

If you would like to have a formal class on using Microsoft Project, here is a link for my classes.

Dale Howard Project MVP
Dale Howard
Microsoft Project MVP “20 Years”

About Me

Hello there Microsoft Project lovers! I’m Dale Howard and I’ve been a Microsoft Project MVP (Most Valuable Professional) for 20 years in a row and I’m currently one of only 26 Project MVPs in the entire world. Pretty exciting, right!?

If you post a question about any of Microsoft’s PPM tools on the public message boards, look to see who the moderator or person that has answered the questions and you see, it’s frequently me answering your questions. Some people like to golf, I love Microsoft Project helping the community get to understand Microsoft Project much better.

I’ve been teaching students at all levels for over 20 years and have taught thousands of users around the world. I’ve written and co-authored 23 books on Microsoft Project, Project Server, and Project Server so if you’re like me and like to read over watching a video, you can Check Out My Books on Amazon.

For the people that like to watch videos, check out my YouTube channel. If you post a question in the comments, I’ll be happy to answer questions or create a new video to answer your question.

If you’ve got a question about Microsoft Project, Project Server, check out some of these community post areas below where I am the moderator and have been answering questions on these message boards for over 20 years.

My Students Include:

parker aerospace
us air force
sandia national laboratories
conoco phillips

Latest Posts

  • Microsoft Project: Risk Management Magic

    Microsoft Project: Risk Management Magic

    Discover how to use Microsoft Project’s “Inactivate Tasks” feature for risk management planning. Learn step by step how to add and inactivate risk tasks, as well as activate them when needed. This innovative approach ensures your project adapts seamlessly to uncertainties.

  • How to Use the Relationship Diagram in Microsoft Project

    How to Use the Relationship Diagram in Microsoft Project

    When used alone, the Relationship Diagram view is practically worthless, but when used in combination with another view, it is incredibly powerful. In this article, I will show you the power of this amazing little view.

  • Mastering Microsoft Project: Enhance Your Task Form View with Custom Sets of Details

    Mastering Microsoft Project: Enhance Your Task Form View with Custom Sets of Details

    In this article, I will teach you about the different sets of details (columns and fields) that are available in the Task Form view, and give you my recommendations on how and when to use each set.

  • Disable Automatic Recalculation in MS Project

    Disable Automatic Recalculation in MS Project

    Stop MS Project from auto-recalculating your schedule. Step-by-step guide to disable automatic recalculation and take back control.

  • Resetting Customized Views in Microsoft Project: A Simple Guide

    Resetting Customized Views in Microsoft Project: A Simple Guide

    Learn how resetting customized views in Microsoft Project to their default view will save you tons of time and pain. Follow these step-by-step instructions to revert back easily.

  • What Causes the Duration to Change in Fixed Duration Tasks?

    What Causes the Duration to Change in Fixed Duration Tasks?

    In this informative article, we delve into the intricacies of Microsoft Project’s Fixed Duration tasks, exploring why their Duration can change unexpectedly. Discover the reasons behind these shifts and gain valuable insights to manage your projects more confidently and efficiently.

  • Project Custom Date Formatting in MS Project

    Project Custom Date Formatting in MS Project

    Change date format in Microsoft Project per file. Master project custom date formatting without altering global settings. Quick guide!

  • Display the Critical Path in Microsoft Planner

    Display the Critical Path in Microsoft Planner

    A key feature of Microsoft Project is the Critical Path. This feature is available in Project for the Web, and I will show you the trick required to display your Critical Path in Project for the Web.

  • Effortlessly Create and Utilize Microsoft Planner Templates

    Effortlessly Create and Utilize Microsoft Planner Templates

    Discover a clever workaround for creating Project for the Web Templates. Streamline your project kickstart process and easily access your favorite projects with this nifty trick.