Mastering Microsoft Project: Enhance Your Task Form View with Custom Sets of Details

Hey there, in this blog post, I’m excited to walk you through a nifty trick that many Microsoft Project users might not know about – the ability to apply different sets of details in the Task Form view. If you’re tired of the same old task view and want to make your project management experience more tailored and efficient, keep reading! I’ll guide you step-by-step on how to do just that. If you would like to watch the YouTube video on this subject, click here or click the thumbnail below.

Companion Articles in This Views, Tables, Filters & Formatting Series: Explore these connected tutorials in the same topic area to build your skills step by step:

Mastering Microsoft Project: Enhance Your Task Form View with Custom Sets of Details

YouTubeWatch the Step-by-Step Video

Prefer to follow along visually? This video demonstrates the exact steps you’ll learn below using Microsoft Project Desktop.

At a Glance: Mastering Microsoft Project: Enhance Your Task Form View with Custom Sets of Details:

  • Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and subscription editions).
  • Key Step / Takeaway 1: Getting Started
  • Key Step / Takeaway 2: Exploring Different Sets of Details
  • Key Step / Takeaway 3: Assigning Resources with Precision
  • Key Step / Takeaway 4: Specifying Task Dependencies Like a Pro
  • Best Practice: Follow the numbered step-by-step instructions below to apply this technique cleanly in your schedule.

Getting Started

Before we dive into the nitty-gritty, make sure you’re in the Task Entry view. To do this, apply the default Gantt Chart view, right-click anywhere in the white part of the Gantt chart screen, and then select the “Show Split” item on the shortcut menu. Now you’ve got the Task Entry view displayed, with Gantt chart view in the top pane and the Task Form view in the bottom pane.

Exploring Different Sets of Details

Now, let’s talk about the heart of the matter – the different sets of details. What are they, you ask? Essentially, a set of details is a collection of fields and columns displayed in the Task Form view. The default set of details is named “Resources and Predecessors,” which is great for assigning resources to tasks. But here’s where the magic happens – you can customize these sets of details to make your project management smoother. Imagine you need to pre-plan overtime work for a task. With the right set of details, you can do that with ease.

Assigning Resources with Precision

  • Let’s say I want to assign Larry Barnes to a task, and he’s working at 25% capacity. Select the task in the Gantt Chart pane, right-click in the Task Form pane, and then select the “Resources and Predecessors” set of details. In the Task Form pane, I can now assign Larry Barnes at a Units value of 25%.
  • Now, there’s a neat companion set of details called “Resources and Successors.” The only difference is that the column “Successor Name” replaces “Predecessor Name.” Same principle, different application.

Specifying Task Dependencies Like a Pro

  • Ever heard of “Predecessors and Successors”? This set of details is gold for specifying task dependency relationships. Say I want the Build task to depend on the Design task. I’ll choose the “Predecessors and Successors” set of details, set the Finish-to-Start (FS) dependency type, and hit OK. Now, my tasks are linked like a charm.

Fine-Tuning Schedules with Schedule Details

  • What if you’re juggling multiple resources with different Start dates? That’s where “Schedule Details” come in. Let’s say that I have three resources assigned to a task. Their names are Terry, Sue, and Ellen. Let’s say Terry starts on day one, Sue starts two days later, and Ellen starts three days after that. All I need to do is to adjust the Delay value for each resource accordingly, hit OK, and watch Microsoft Project smartly reschedule everything.

Powering Up with Work Details

  • Planning overtime? The “Work Details” set of details is your new best friend. I’ve got Jerry King assigned to a task for 20 days, but we need to speed things up. All I need to do is to enter the extra hours of overtime work in the Overtime field, hit OK, and watch the Duration shrink as Microsoft Project works its magic.

Peeking into Costs

  • The “Costs” set of details is more for viewing than altering. If you want to see how much a resource’s work is costing you, this set of details has you covered. Baseline Cost, Actual Cost, and Remaining Cost are neatly laid out for your review in this set of details.

Unearthing Task Notes with Notes Details

  • Lastly, there’s the “Notes” set of details, which reveals any notes attached to the task. It’s super useful for keeping track of those extra tidbits of information.

Return to the Default Set of Details

  • After you’ve explored these different sets of details, it’s wise to return to the default “Resources and Predecessors” set. It’s like your safe harbor amidst the sea of options.

And there you have it – the secret sauce to elevating your Microsoft Project game. These sets of details aren’t just features; they’re your ticket to customizing your project management experience. From resource assignments to dependencies, schedules to costs, you’re now equipped with a toolbox of efficiency-boosting techniques.

If you have questions, please add them in the Comments section below. Or if you watch the video, add your questions or comments there. Please subscribe to my YouTube channel and leave “Likes” if you like the videos.

If you would like to have a formal class on using Microsoft Project, here is a link for my classes.

Leave a Reply

Your email address will not be published. Required fields are marked *

Are you human? Please solve:Captcha


Table of Contents

Add a header to begin generating the table of contents

Need Microsoft Project Training?

Microsoft Desktop Training $399 with Dale Howard MVP

Project Server Training

Project Server Training with Dale Howard MVP

1-on-1 Training

Get 1-on-1 Private Training with Dale Howard MVP