How to Reschedule Incomplete Work in Microsoft Project for Accurate Forecast Dates

In this blog post, I’m going to show you how (and why) to reschedule incomplete work from the past into the current reporting period in Microsoft Project. If you enter weekly task progress in your schedule but skip rescheduling uncompleted work past your Status Date, your project’s forecast Finish date is almost certainly wrong!

Companion Articles in This Baselines, Variance & Progress Tracking Series: Explore these connected tutorials in the same topic area to build your skills step by step:

How to Reschedule Incomplete Work in Microsoft Project for Accurate Forecast Dates

YouTubeWatch the Step-by-Step Video

Prefer to follow along visually? This video demonstrates the exact steps you’ll learn below using Microsoft Project Desktop.

At a Glance: Rescheduling Incomplete Work in Microsoft Project:

  • Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and Project Online Desktop Client).
  • The Problem: When tasks fall behind, any light-blue unfinished portion of a Gantt bar sitting to the left of the red dashed Status Date gridline represents incomplete work in the past, which makes your overall project Finish date artificially optimistic.
  • The 1-Click Fix: Click Project -> Update Project, choose Reschedule uncompleted work to start after (which automatically defaults to your Status Date), keep Entire project selected, and click OK.
  • What Microsoft Project Does Behind the Scenes: Partially completed tasks receive a dotted Task Split (...) to push remaining work into the current week, while unstarted tasks receive a Start No Earlier Than (SNET) constraint after the Status Date.

Need hands-on help with your schedule? Explore my $399 Microsoft Project Desktop Course, Project Server Training, or book 1-on-1 Private Training & Consulting.

What Is “Incomplete Work in the Past” (and Why Does It Ruin Your Forecast Finish Date)?

Let’s look at a common weekly status update scenario in the Gantt Chart view:

  • The thin green vertical gridline is the Current Date (Wednesday, June 11th).
  • The red dashed vertical gridline is the project Status Date (Friday, June 6th), which is the end of the previous reporting week.
  • On the Design 1 task, Mickey Cobb completed 100% of her work last week as planned (shown by the solid dark-blue progress bar filling the entire Gantt bar).
  • On the Design 2 task, Calvin Baker was pulled off the project part-time last week and completed only 50% of his scheduled work. The left half of his Gantt bar has a dark-blue progress stripe, while the right half is still light blue, sitting to the left of the Friday, June 6th Status Date!
  • On the Design 3 task, Henry Baum was out on sick leave all week and completed 0% of his task. The entire light-blue Gantt bar is sitting in last week, to the left of the Status Date!

Right now, the project’s overall forecast Finish date still reads June 24th. Is June 24th an accurate forecast finish date? No! Unless you own a time machine, Calvin and Henry cannot go back into last week to finish that uncompleted work. To generate an accurate forecast schedule, you must push that incomplete work from the past into the current reporting period.

How Do I Reschedule Incomplete Work into the Current Reporting Period?

Once you have set your Status Date (Project -> Status Date) and entered all actual progress for the reporting period, follow these steps to reschedule any remaining past work:

  1. Click the Project ribbon tab.
  2. In the Status section at the right end of the ribbon, click the Update Project button to open the Update Project dialog.
  3. In the Update Project dialog:
    1. Select the second radio button option: Reschedule uncompleted work to start after:.
    2. Confirm the date field displays your current Status Date (as a courtesy, Microsoft Project automatically fills in your Status Date, such as 6/6/25, for you!).
    3. Leave the For: Entire project option selected so Microsoft Project automatically finds every task with unfinished work prior to the Status Date (or choose Selected tasks if you prefer to update one task at a time).
    4. Click OK.

What Happens to Your Tasks When You Click OK?

Watch how task dates move in the Gantt Chart screen the instant you click OK:

  1. In-Progress Tasks Get a Task Split (...): On the Design 2 task (which was 50% complete), Microsoft Project leaves the completed dark-blue work in last week, inserts a dotted Task Split (...) up to the Status Date, and pushes the remaining light-blue incomplete work into Monday of the current week!
  2. Unstarted Tasks Get a Start No Earlier Than Constraint: On the Design 3 task (which had 0% progress), Microsoft Project moves the entire Gantt bar out of last week into Monday of the current week by applying a Start No Earlier Than (SNET) constraint.
  3. Downstream Dependent Tasks Shift to Reveal the True Finish Date: Because the Design 2 and Design 3 tasks pushed into the current week, their successors shift accordingly, moving the project’s overall forecast Finish date from June 24th to June 27th!

Now you have an honest, realistic forecast schedule you can present to your project sponsor and stakeholders with confidence.

Frequently Asked Questions

What is the difference between the two options in the Update Project dialog?

The first option in the Update Project dialog (Update work as complete through) tells Microsoft Project to mark tasks as completed up to the Status Date, assuming everything went according to plan. The second option (Reschedule uncompleted work to start after) does the opposite: after you have already entered actual progress, it takes whatever work did not get done prior to the Status Date and moves it forward to start after the Status Date.

Why did a calendar icon appear in the Indicators column after I ran Update Project?

When an unstarted task (0% Complete) is scheduled prior to the Status Date and has no predecessor pushing it forward, Update Project moves the task after the Status Date by applying a Start No Earlier Than (SNET) constraint set to the next working day after the Status Date. That constraint displays a small calendar icon in the Indicators column.

Should I set the Status Date before or after entering task progress?

Always set the Status Date (Project -> Status Date) first (typically the Friday, Saturday, or Sunday at the end of last week’s reporting period) and display the red dashed Status Date gridline in the Gantt Chart screen. Next, enter your team’s actual progress for that period, and finish by running Project -> Update Project -> Reschedule uncompleted work to start after.


Ready to master Microsoft Project? If you found this article helpful, check out my free tutorials on my YouTube channel, download my Free Microsoft Project Quality Filters, or explore my structured, expert-led training courses and 1-on-1 coaching at dalehowardmvp.com.