How to Enter Lag Time in Calendar Days in Microsoft Project

In this blog post, I’m going to show you the secret code for entering Lag time in calendar days (eDays) instead of working days (d) on a task dependency in Microsoft Project. Have you ever added a 20-day vendor shipping delay to a task dependency, only to watch the successor task jump four full weeks (28 calendar days) into the future because Microsoft Project skipped over every weekend?

Companion Articles in This Calendars, Holidays & Working Time Series: Explore these connected tutorials in the same topic area to build your skills step by step:

How to Enter Lag Time in Calendar Days in Microsoft Project

YouTubeWatch the Step-by-Step Video

Prefer to follow along visually? This video demonstrates the exact steps you’ll learn below using Microsoft Project Desktop.

At a Glance: Entering Lag Time in Calendar Days (ed):

  • Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and Project Online Desktop Client).
  • The Default Behavior (d): Entering 20d of Lag time adds 20 working days (Monday through Friday), which spans 4 full weeks on a standard calendar.
  • The Calendar-Day Secret (ed): Changing the lag unit from d to ed (elapsed days) tells Microsoft Project to count 24-hour calendar days with zero non-working time (including Saturdays, Sundays, and holidays).
  • How to Enter It: Type 1FS+20ed directly into the Predecessors cell, or double-click the link line between the Gantt bars to open the Task Dependency dialog and enter 20ed in the Lag field.

Need hands-on help with your schedule? Explore my $399 Microsoft Project Desktop Course, Project Server Training, or book 1-on-1 Private Training & Consulting.

Why Does Standard Lag Time Push Tasks Too Far into the Future?

Suppose you have a simple two-task sequence in your project:

  • Task 1: Order Hardware
  • Task 2: Set Up Hardware (linked with a Finish-to-Start dependency from Task 1)

Your historical records show that once the hardware is ordered, it takes your vendor 20 days to ship and deliver the equipment. If you double-click the link line arrowhead between the two Gantt bars to open the Task Dependency dialog and type 20d into the Lag box, Microsoft Project creates a massive gap on the Gantt Chart!

Why did your task dates move a full month out? Because by default, 20d means 20 working days (Monday through Friday according to the Project Calendar). However, your hardware vendor ships 24/7, and trucks roll right through the weekend! What you actually need is 20 calendar days of Lag time.

How Do I Change Lag Time from Working Days (d) to Calendar Days (ed)?

To tell Microsoft Project to count continuous 24-hour calendar days (including weekends and company holidays) on a dependency lag, use the ed (elapsed days) duration code:

  1. In the Gantt Chart view, click in the Predecessors cell for the successor task (for example, Set Up Hardware on Row 2).
  2. Look at the dependency code Microsoft Project displays in that cell: 1FS+20d (Task 1, Finish-to-Start, plus 20 working days of lag).
  3. Click inside the cell to edit the text and change d to ed so the value reads:

1FS+20ed

  1. Press the Enter key.

Bingo! Watch the Gantt bar for Set Up Hardware immediately snap back by 8 calendar days! Instead of counting 20 Monday-through-Friday working days across four weeks, Microsoft Project now counts 20 continuous 24-hour elapsed days (6 days in week one + 7 days in week two + 7 days in week three = 20 calendar days).

Alternative Method: Using the Task Dependency Dialog

If you prefer using a dialog instead of editing the Predecessors cell directly:

  1. Place your mouse pointer directly on the link line between the two Gantt bars in the Gantt Chart screen (aim for the little arrowhead, since that is the thickest part of the link line) and double-click.
  2. In the Task Dependency dialog:
    1. Confirm the Type pick list button is set to your desired dependency (such as Finish-to-Start (FS)).
    2. In the Lag field, type 20ed.
    3. Click OK.

When Should You Use Elapsed Days (ed) for Lag Time?

Using elapsed duration codes (ed for elapsed days, ew for elapsed weeks, eh for elapsed hours) on Lag time is ideal whenever a waiting period runs 24/7 outside of your team’s normal Monday-through-Friday work week:

  • Vendor Shipping and Transit Times: Equipment or material shipments that travel over weekends (1FS+14ed).
  • Physical or Chemical Processes: Concrete curing, paint drying, or lab incubation periods (3FS+7ed).
  • Contractual or Regulatory Review Windows: Mandatory 30-calendar-day government permit or legal notice periods (5FS+30ed).

(Note: If an unexpected delay hits your project after your baseline is saved and you want executives to see a labeled delay bar on the Gantt Chart, consider inserting a zero-resource Dummy Task with elapsed duration instead of hiding the delay in Lag time!)

Frequently Asked Questions

What does ed stand for in Microsoft Project?

In Microsoft Project, ed stands for elapsed days. An elapsed day is a continuous 24-hour calendar day that ignores non-working weekends and holidays on the Project Calendar. You can also use eh (elapsed hours), ew (elapsed weeks), and emo (elapsed months).

Can I enter Lead time (negative Lag) in calendar days too?

Yes! To overlap two tasks using calendar days rather than working days, enter a negative elapsed day value in the Predecessors column or Task Dependency dialog, such as 1FS-5ed.

How can I find all tasks in my schedule that use elapsed days (ed)?

Because elapsed durations and elapsed lag times can sometimes cause tasks to start or finish over a weekend, you can build a custom filter to find elapsed days (edays) or download my Free Microsoft Project Quality Filters to audit every dependency lag in your project in one click.


Ready to master Microsoft Project? If you found this article helpful, check out my free tutorials on my YouTube channel, download my Free Microsoft Project Quality Filters, or explore my structured, expert-led training courses and 1-on-1 coaching at dalehowardmvp.com.