In this blog post article, I’ll guide through an easy way of Finding Tasks Ahead of Schedule. For example, if you have a task that was supposed to be 50% completed by a certain date, but is actually 75% done, that task is considered ahead of schedule. Let’s dive into the steps to easily locate such tasks.
If you would rather watch a YouTube video on this subject, click here or click the thumbnail below.

Finding Tasks Ahead of Schedule: Background Information
To locate tasks that are ahead of schedule, you need to make sure you have set the Status date for your project. The Status date represents the last day of last week’s reporting period. Generally, the Status date is last Friday, Saturday, or Sunday.
To find tasks that are ahead of schedule, you need to identify tasks whose progress bar extends beyond the Status date. The progress bar, by the way, is the darker blue bar running through the middle of each Gantt bar in the Gantt Chart view, such as shown in the following illustration. The red dashed vertical gridline, by the way, represents the Status date for the project.

In the preceding illustration, notice how the progress bar for the third and fourth tasks extends to the right of the Status date gridline. These two tasks have progress that is ahead of schedule. To locate tasks like this, I need to determine the date on which progress bar ends for each task, and then filter for tasks whose progress bar ending date is greater than the Status date of the project. But how can you find out the date on which the task’s progress bar ends?
Amazingly enough, Microsoft Project offers a default column containing this very information: the Stop column. The Stop column displays the date on which the progress bar ends for each task. So, In theory, all I should need to do is to create a filter that tests for the Stop date being greater than the Status date.
But no, it’s not that easy! This is because you cannot filter for the Status date in the Filter Definition dialog, as it is not an available field. In this dialog, you can only filter for Task information, but the Status date is Project information. But I have a trick to show you, which is to create a custom Date field that captures the Status date of the project and displays it for every task.
Creating a Custom Date Field
Complete the following steps to create the custom Date field:
- Click on the Project tab to display the Project ribbon.
- Click the Custom Fields button to open the Custom Fields dialog.
- Click the Type pick list button and select the Date item on the list.
- Choose an available Date field, such Date 1, and then click the Rename… button.
- In the Rename Field dialog, enter a name such as Status Date 2, and then click the OK button.
- Click the Formula button to display the Formula dialog for the custom Date field.
- Enter [Status Date] in the Formula dialog and then click the OK button.
- Select the Use formula option in the Calculation for Task and Group Summary Rows section of the dialog.
- Click the OK button to create the custom Status Date 2 field.
At this point, the custom Status Date 2 field is ready to use.
Creating and Applying the Custom Filter
Complete the following steps to create a custom filter to locate tasks whose progress is ahead of schedule:
- Click the View tab to display the View ribbon.
- Click the Filter pick list button and select the New Filter item.
- Name the new filter Progress in the Future.
- Select the Stop field in the Field Name column, select the “is greater than” value in the Test column, and use the Status Date 2 field in the Value(s) column.
- Select the Show related summary rows checkbox and then click the Save button to create the filter.
In the More Filters dialog, select the new custom field and click the Apply button. Microsoft Project will now display only those tasks whose progress is ahead of schedule.
Saving the Custom Filter and Field for Future Projects
To use the custom Date field and the custom filter in all current and future projects, complete the following additional steps:
- Click the File tab to display the Backstage.
- Click the Info tab and then click the Organizer button.
- In the Organizer dialog, click the Filters tab, select the custom Progress in the Future filter in the list on the right side of the dialog, and click the Copy button.
- Click the Fields tab, select Status Date 2 custom field in the list on the right side of the dialog, and click the Copy button.
- Click the Close button to close the Organizer dialog and then press the Escape key on your computer keyboard to exit the Backstage.
You have just saved both the custom filter and custom field in your global .MPT file, which will allow you to use them in all current and future projects.
Now, you have the tools to quickly locate tasks with progress ahead of schedule in any project you manage. If you have questions, please add them in the “Leave a Reply” section below. Or if you watched the video, add your questions or comments there. Please subscribe to my YouTube channel and leave “Likes” if you like the videos.
If you would like to have a formal class on using Microsoft Project, here is a link for my classes.

Dale Howard
Microsoft Project MVP “20 Years”
About Me
Hello there Microsoft Project lovers! I’m Dale Howard and I’ve been a Microsoft Project MVP (Most Valuable Professional) for 20 years in a row and I’m currently one of only 26 Project MVPs in the entire world. Pretty exciting, right!?
If you post a question about any of Microsoft’s PPM tools on the public message boards, look to see who the moderator or person that has answered the questions and you see, it’s frequently me answering your questions. Some people like to golf, I love Microsoft Project helping the community get to understand Microsoft Project much better.
I’ve been teaching students at all levels for over 20 years and have taught thousands of users around the world. I’ve written and co-authored 23 books on Microsoft Project, Project Server, and Project Server so if you’re like me and like to read over watching a video, you can Check Out My Books on Amazon.
For the people that like to watch videos, check out my YouTube channel. If you post a question in the comments, I’ll be happy to answer questions or create a new video to answer your question.
If you’ve got a question about Microsoft Project, Project Server, check out some of these community post areas below where I am the moderator and have been answering questions on these message boards for over 20 years.
Microsoft Tech Community
Reddit Project Server Community
LinkedIn Project and Planner Group
My Students Include:




Latest Posts
-
Customize Your Microsoft Project Quick Access Toolbar; Fast and Easy!
In this article, you will learn how to customize the Quick Access Toolbar in Microsoft Project with a selection of commands that will make it much easier to use this powerful tool.
-
Creating Cross-Project Dependencies in Microsoft Project: A Step-by-Step Guide
Learn the fastest method for creating cross-project dependencies in Microsoft Project. Follow these steps to easily establish task dependencies between projects.
-
How to Identify and Remove Microsoft Project Filters
Discover how to identify and remove Microsoft Project Filters that may be causing missing tasks and ID numbers in your project. Read on to learn more!
-
Easily Reassign Task Assignments in Microsoft Project
Learn how to easily reassign task assignments in Microsoft Project using the drag-and-drop feature in the Resource Usage view. Streamline your projects today!
-
How to Hide the Default Task Mode Indicator in Microsoft Project
Are you tired of the annoying Default Task Mode indicator in Microsoft Project? Learn how to hide it with this quick and simple trick. Let’s dive in!
-
Display the Work Breakdown Structure in the Resource Usage View
Discover the game-changing trick in Microsoft Project that uncovers the Work Breakdown Structure (WBS) of summary tasks in the Resource Usage view. Revolutionize your project analysis, gain a deeper understanding of tasks, and boost productivity with this powerful technique.
-
Is In-Person Microsoft Project Training Better?
Looking to boost your skills in Microsoft Project? In-person training offers interactive learning, personalized instruction, and real-world scenarios for a comprehensive learning experience.
-
Microsoft Project: Cancel Unneeded Tasks in Microsoft Project PROFESSIONAL
Learn how to effectively cancel unneeded tasks in Microsoft Project using the Inactivate Task feature. This professional version tool not only saves you time but also eliminates confusion about negative variances in your project.
-
Faster Microsoft Project Planning with Virtual Columns
Discover the hidden power of the Add New Column virtual column in Microsoft Project. Enhance your project management experience with this nifty feature.