How to Create and Format a Timeline View in Microsoft Project

In this blog post, I’m going to walk you through how to create, customize, and export an executive-ready Timeline view in Microsoft Project step by step. When senior executives or clients ask for a one-page overview of your project, they don’t want to read a 500-row Gantt Chart: they want a clean, visual roadmap showing your major Phases, Deliverables, and Milestones.

Companion Articles in This Reports, Timelines, Excel & Printing Series: Explore these connected tutorials in the same topic area to build your skills step by step:

How to Create and Format a Timeline View in Microsoft Project

YouTubeWatch the Step-by-Step Video

Prefer to follow along visually? This video demonstrates the exact steps you’ll learn below using Microsoft Project Desktop.

At a Glance: Creating a Timeline View in Microsoft Project:

  • Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and Project Online Desktop Client).
  • Step 1: Display the Timeline pane above the Gantt Chart (View ribbon tab -> check Timeline in the Split View section).
  • Step 2: Click inside the Timeline pane, click Timeline Format -> Existing Tasks, and select the checkboxes for your key Phases, Deliverables, and Milestones in the Add Tasks to Timeline dialog.
  • Step 3: Select cramped or overlapping tasks on the Timeline and click Display as Callout so their labels float cleanly above or below the timeline bar.
  • Step 4: Color-code individual Timeline bars using the Background Color bucket and click Copy Timeline to paste a high-resolution roadmap directly into PowerPoint or Outlook!

Need hands-on help with your schedule? Explore my $399 Microsoft Project Desktop Course, Project Server Training, or book 1-on-1 Private Training & Consulting.

Step 1: How Do I Display the Timeline Pane in Microsoft Project?

By default, the Timeline pane sits right above the Gantt Chart view. If someone previously closed or hid it in your project file, here is how to turn it back on:

  1. Click the View ribbon tab.
  2. Look in the Split View section on the right side of the ribbon and select the Timeline checkbox.
  3. Float your mouse cursor over the gray divider bar between the Timeline pane and the Gantt Chart screen until it turns into a two-headed arrow, then drag it down slightly to give yourself plenty of room to build your Timeline view.

Step 2: How Do I Add Phases, Deliverables, and Milestones to the Timeline?

Microsoft Project gives you two fast ways to add tasks from your schedule onto the Timeline bar. When adding tasks to a whole-project roadmap at one time, the Existing Tasks dialog is by far the fastest method:

  1. Click anywhere inside the white Timeline pane at the top of the screen so the Timeline Format ribbon tab appears.
  2. Click the Timeline Format ribbon tab and click the Existing Tasks button in the Insert section.
  3. In the Add Tasks to Timeline dialog:
    1. Scroll through your Work Breakdown Structure outline.
    2. Select the checkboxes next to your top-level Phases (Summary Tasks), key Deliverables, and major Milestones.
    3. Click OK.

(Tip: You can also add individual tasks from the Gantt Chart pane at any time by right-clicking a task row and clicking the Add to Timeline item on the shortcut menu.)

Step 3: How Do I Fix Cramped Tasks Using “Display as Callout”?

Once your Phases, Deliverables, and Milestones appear on the Timeline bar, you will often notice that shorter tasks overlap or look squished inside the bar, cutting off their task names. You can fix that using Callouts:

  1. Click directly on a cramped or overlapping task bar inside the Timeline pane (or hold down the Ctrl key and click multiple task bars).
  2. On the Timeline Format ribbon tab, look in the Current Selection section and click Display as Callout (or right-click the bar in the Timeline pane and click the Display as Callout item on the shortcut menu).
  3. Drag the callout text above or below the Timeline bar so every task name and date range is 100% readable.

Step 4: How Do I Color-Code Timeline Bars and Copy to PowerPoint?

To make your executive Timeline pop during steering committee presentations, customize the bar colors and copy the Timeline image to your clipboard:

  1. In the Timeline pane, click a Timeline bar or hold down Ctrl to select multiple bars that share a theme.
  2. On the Timeline Format ribbon tab, in the Font section:
    1. Click the Background Color (paint bucket) pick list button and choose a soft pastel or bold accent color for that phase.
    2. If you choose a dark background color, click the Font Color pick list button and change the text color to White so the label stays easy to read.
  3. When your Timeline looks the way you want it, click Copy Timeline in the Copy section of the Timeline Format ribbon tab and choose one of three sizes:
    1. For E-mail: Compact size (approximately 60% of full size) designed to fit neatly inside an Outlook email message.
    2. For Presentation: Medium size (approximately 80% of full size), designed for a landscape Microsoft PowerPoint slide.
    3. Full Size: Maximum resolution for large monitors or printed posters.
  4. Switch to PowerPoint, Word, or Outlook and press Ctrl + V (Paste) to drop your finished executive roadmap right onto the slide!

Frequently Asked Questions

If I remove a task from the Timeline, does it delete the task from my project schedule?

No! Never press the Delete key while a task is selected in the Gantt Chart! Instead, click the task bar inside the Timeline pane and click Remove from Timeline in the Current Selection section of the Timeline Format ribbon tab (or right-click the bar on the Timeline and click the Remove from Timeline item on the shortcut menu). That simply hides the task from the Timeline while leaving your schedule 100% intact.

Can I create multiple Timeline bars in a single Timeline view?

Yes! Beginning in Microsoft Project 2016 (and available in 2019, 2021, 2024, and Project Online Desktop Client), you can click inside the Timeline pane and click Timeline Bar in the Insert section of the Timeline Format ribbon tab. This adds a second or third stacked Timeline bar so you can display different phases, workstreams, or fiscal years on separate horizontal bars!

Do Timeline dates update automatically when my schedule changes?

Yes! Every bar, callout, and milestone diamond on the Timeline is dynamically linked to the underlying task in your schedule. Whenever a task’s Start or Finish date moves in the Gantt Chart, the Timeline updates automatically. However, once you paste a copied Timeline into PowerPoint, that pasted graphic is a static image snapshot.

How do I hide the tick marks or task dates on the Timeline to save space?

Click inside the Timeline pane, open the Timeline Format ribbon tab, and look in the Show/Hide section. Unchecking Task Dates removes the Start and Finish dates from every bar and callout on the Timeline, giving you a much cleaner layout when presenting a crowded schedule.


Ready to master Microsoft Project? If you found this article helpful, check out my free tutorials on my YouTube channel, download my Free Microsoft Project Quality Filters, or explore my structured, expert-led training courses and 1-on-1 coaching at dalehowardmvp.com.

Leave a Reply

Your email address will not be published. Required fields are marked *

Are you human? Please solve:Captcha