How to Create a 6-Day Work Week in Microsoft Project

Have you ever needed to create a 6-day work week in Microsoft Project, such as making Saturday a working day for your schedule? This is a common requirement for organizations that work extended hours or non-standard schedules.

In this article, I’ll show you how to configure your calendars in Microsoft Project so you can create a 6-day work week, while also explaining a few best practices to avoid common scheduling mistakes.

If you would rather read a similar article that includes screenshots, click here or click the thumbnail below.

Step-by-Step on LinkedIn

Prefer to follow along visually? This video demonstrates the exact steps you’ll learn below using Microsoft Project Desktop.

Schedule Every Task Using a 6-Day Work Week in Microsoft Project

Let’s start with the scenario where you want every task in your project to follow a 6-day work week, spanning from Monday through Saturday. Here’s how you can make that happen:

  1. Open the project you want to work on.
  2. Click on the “Project” tab to reveal the Project ribbon.
  3. In the “Properties” section, click the “Change Working Time” button. This opens the “Change Working Time” dialog with the default “Standard” calendar selected.
  4. Click the “Work Weeks” tab. In the data grid, you’ll see the [Default] item, which defines the default working schedule for the Standard calendar. By default, it’s set to Monday through Friday, from 8:00 AM to 12:00 PM and 1:00 PM to 5:00 PM, with Saturdays and Sundays marked as nonworking time.
  5. Leave the [Default] item selected and click the “Details” button. A new dialog, “Details,” will pop up.
  6. In this “Details” dialog, choose Saturday from the “Select day(s)” list.
  7. Select “Set day(s) to these specific working times” and define your Saturday working hours in the “From” and “To” grid. For example, set it as 8:00 AM to 12:00 PM and 1:00 PM to 5:00 PM.
  8. Click “OK” to close the “Details” dialog. The “Change Working Time” dialog now reflects the updated working schedule, from Monday through Saturday.
  9. Click “OK” again to close the “Change Working Time” dialog.

Microsoft Project will automatically update the working schedule for all tasks in your project to follow this new Monday through Saturday working schedule. You’ll also notice that the software displays a gray shaded band only on Sundays in the Gantt Chart screen, indicating that Sunday is the only nonworking day each week.

But wait, we’re not done yet! After updating the Standard calendar, you need to adjust a specific scheduling option in the Project Options dialog.

  1. Click on the “File” tab and then select “Options” in the lower-left corner of the Backstage.
  2. In the “Project Options” dialog, go to the “Schedule” tab.
  3. On the “Schedule” page, change the “Hours per week” option to 48 and then click the “OK” button.

This change ensures that if you enter a Duration value in Weeks for a task, Microsoft Project will correctly schedule it using a 6-day work week, rather than a 5-day work week. For example, if you enter a Duration value of 2 Weeks, the software will schedule the task as 12 working days, not 10.

Schedule Specific Tasks Using a 6-Day Work Week

Now, if you need most tasks in your project to stick to a 5-day work week, but certain tasks require a 6-day work week, you can create a new base calendar for those special tasks. Follow these steps:

  1. Click on the “Project” tab to display the Project ribbon.
  2. In the “Properties” section, click the “Change Working Time” button. This opens the “Change Working Time” dialog.
  3. In the upper-right corner of the dialog, click the “Create New Calendar” button.
  4. Click it and, in the “Create New Base Calendar” dialog, choose to make a copy of the Standard calendar.
  5. Give your new calendar a name like “6-Day Work Week” and click “OK.”
  6. In the “Change Working Time” dialog, click the “Work Weeks” tab.
  7. Select the [Default] item in the Work Weeks grid and click “Details.”
  8. In the “Details” dialog, pick Saturday from the “Select day(s)” list.
  9. Select “Set day(s) to these specific working times” and define the Saturday working hours, like 8:00 AM to 12:00 PM and 1:00 PM to 5:00 PM.
  10. Click “OK” to close the “Details” dialog. Now, the “Change Working Time” dialog displays the new default working schedule for your custom base calendar, Monday through Saturday.
  11. Click “OK” to close the “Change Working Time” dialog.

Applying the New Base Calendar as a Task Calendar

So, how do you apply this new custom base calendar to specific tasks that need a 6-day work week? Here’s how:

  1. Double-click on the task whose schedule you want to change to the 6-day work week. This opens the “Task Information” dialog.
  2. In the “Task Information” dialog, switch to the “Advanced” tab.
  3. In the “Advanced” page, click the “Calendar” pick list and select your custom base calendar with the 6-day work week. Also, select the “Scheduling ignores resource calendars” checkbox.
  4. While you’re in the “Task Information” dialog, head over to the “Notes” tab.
  5. Here, you can add a note explaining why you applied the base calendar to this task.
  6. Click the “OK” button to save your changes and close the “Task Information” dialog.

Once you’ve applied the custom base calendar as a Task calendar, the task will be rescheduled to reflect a 6-day work week that includes Saturdays as working days.

Copying Calendars to the Global.mpt File

Lastly, if you want to make this updated Standard calendar or the new custom base calendar available in all your future projects, follow these steps to copy it to the Global.mpt file:

  1. Click on the “File” tab and then select “Info” in the Backstage.
  2. In the “Organize Global Template” section on the Info page, click the “Organizer” button.
  3. In the “Organizer” dialog, go to the “Calendar” tab to see the Calendar page.
  4. In your active project (on the right side of the dialog), select either the Standard calendar or your new custom base calendar. Choose the Standard calendar only if you made changes to it.
  5. In the middle of the Organizer dialog, click the “Copy” button.
  6. If you’re copying the Standard calendar, you’ll see a confirmation dialog. Click “Yes” to overwrite the Standard calendar in the Global.mpt file.
  7. Close the Organizer dialog.
  8. Don’t forget to save your latest changes to your project.

And there you have it! You’ve successfully made Saturday a working day in Microsoft Project and learned how to apply this to both your entire project and specific tasks. Plus, you now know how to make these calendar changes available for all your future projects. Happy scheduling!

If you have questions, please add them in the Comments section below. Please check out my other blogs and my YouTube channel. If you would like to have a formal class on using Microsoft Project, here is a link for my classes.

Related Microsoft Project Topics

Microsoft Project Task Constraints

There is one right way to set task Project Task Constraints in Microsoft Project, and one WRONG way to do this. In this blog post article, learn the correct way to set a task constraint.
Read More
0 responses to “How to Create a 6-Day Work Week in Microsoft Project”

Leave a Reply

Your email address will not be published. Required fields are marked *


Need Microsoft Project Training?

Microsoft Desktop Training $399 with Dal

1-on-1 Training

Get 1-on-1 Private Training with Dale Howard MVP

* Popular Topics

Print Your Schedule in Microsoft Project
Learn how to Easily Print Your Schedule for your stakeholders.