Are your project schedules cluttered? Does it make it hard to focus on key phases? Would you like to hide tasks in Microsoft Project when you need to show just the Development and Testing tasks to stakeholders – without deleting (or restoring) anything else?
In this article, I’ll show you my favorite trick to hide tasks in your Microsoft Project using the built-in “Marked” column: a simple filter that hides tasks temporarily. It’s saved me hours in client meetings and still works flawlessly in Microsoft Project through Microsoft 365 (updated and tested December 2025).
Follow these 7 quick steps below or click here to watch the 2-minute video on my Youtube channel or click the image below.
Companion Articles in This Views, Tables, Filters & Formatting Series: Explore these connected tutorials in the same topic area to build your skills step by step:
- Current Article (You Are Here): Hide Tasks in Microsoft Project (No Deleting)
- Companion Tutorial: Remove Resource Names from Gantt Chart in Microsoft Project
- Companion Tutorial: How to Hide Summary Tasks and Outline Numbers in Microsoft Project
- Companion Tutorial: How to Add and Remove Columns in Microsoft Project
- Full Topic Hub: Browse All Views, Tables & Formatting Tutorials →
At a Glance: Hide Tasks in Microsoft Project (No Deleting):
- Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and subscription editions).
- Key Step / Takeaway 1: Hide Tasks in Microsoft Project: Understand the Purpose
- Key Step / Takeaway 2: Step-by-Step: Hide Tasks Using the Marked Column
- Key Step / Takeaway 3: Want more tips? Here's the Latest Posts
- Best Practice: Follow the numbered step-by-step instructions below to apply this technique cleanly in your schedule.
Hide Tasks in Microsoft Project: Understand the Purpose
Imagine you have an important meeting with project stakeholders, and you only want to show them tasks from the Development and Testing section of your project. You will need to hide all other tasks to make the presentation more focused.
Step-by-Step: Hide Tasks Using the Marked Column
- Open your project in Microsoft Project (desktop version).
- Insert the Marked column
Right-click any column header (e.g., Duration) → Insert Column → type “Marked” → select Marked → OK. - Mark the tasks you want to KEEP visible
In the new Marked column, change the cells from “No” to Yes for every task you want to show.
(Tip: You can drag-fill or multi-select rows, then type “Yes” once.) - Apply the filter
Click the dropdown arrow in the Marked column header → uncheck (No) → leave only (Yes) checked → OK.
Only your marked tasks remain visible. - (Optional) Hide the Marked column
Right-click the Marked column header → Hide Column for a completely clean look. - To show everything again
Just press F3 (or View tab → Filter → No Filter).
That’s literally it. No tasks are deleted, nothing is changed permanently, and the filter travels with the file.
This little trick can be a real time-saver when you’re preparing for presentations or meetings. I hope you found this blog post article helpful. If you did, consider subscribing to my YouTube channel for more useful tips and tricks. Don’t forget to hit the notification bell to stay updated on new content. If you have any questions or comments, feel free to share them in the Comment section below. Thanks for reading!
Frequently Asked Questions
Does this hide subtasks too?
Yes – if you mark the parent task “Yes,” subtasks hide with it. For granular control, mark them individually.
How do I unhide everything?
Just press F3 (Clear Filter) or go to View > Filter > No Filter. All tasks reappear instantly.
Will this work in Microsoft Planner or Planner?
The Marked filter is desktop-only (Project 2016+). For web versions, use Groups or export to Excel for filtering.
Alternative: Hide via Outline Levels?
For summary tasks, collapse with the +/- icons (View > Outline > All Subtasks). But Marked is better for non-hierarchical hiding.
Want more tips? Here’s the Latest Posts
-
Baselines, Variance & Progress Tracking, Microsoft Project (All Articles), Microsoft Project Professional, Views, Tables, Filters & Formatting
·
How to Use the Status Date and Late Tasks Filter to Update Progress in Microsoft Project
In this blog post, I’m going to show you how to use the Status Date, a solid red Status Date gridline, and the built-in Late Tasks filter to update project progress like a pro in Microsoft Project. If you have been scrolling up and down a huge project schedule every Friday afternoon trying to figure…
-
Microsoft Project (All Articles), Microsoft Project Professional, Views, Tables, Filters & Formatting
·
How to Display a High-Level Executive Schedule in Microsoft Project
In this blog post, I’m going to show you two fast, reliable ways to display a high-level executive schedule in Microsoft Project. When you walk into a steering committee meeting with a 400-line schedule, executives don’t want to scroll through hundreds of granular work packages; they want to see your high-level Phases, Deliverables, and key…
-
Microsoft Project (All Articles), Microsoft Project Professional, Resources, Assignments & Cost Management
·
How to Create and Assign Material Resources in Microsoft Project (Fixed vs. Variable Consumption Rates)
In this blog post, I’m going to show you how to create and assign Material Resources in Microsoft Project, including the critical difference between a Fixed Consumption rate and a Variable Consumption rate. If your projects involve physical consumables (such as concrete, steel, lumber, bricks, network cable, or fuel), Material Resources let you track both…
-
Calendars, Holidays & Working Time, Microsoft Project (All Articles), Microsoft Project Professional, Resources, Assignments & Cost Management
·
Why Are My Task Dates Moving in Microsoft Project? Troubleshooting Calendar and Resource Issues
In this blog post, I’m going to show you how to troubleshoot the four most common reasons task dates and durations suddenly move in Microsoft Project. Few things frustrate a project manager more than carefully setting up a task’s Duration, Start, and Finish dates, only to watch those dates or durations jump unexpectedly the moment…
-
Baselines, Variance & Progress Tracking, Microsoft Project (All Articles), Microsoft Project Professional
·
How to Do Rolling Wave Planning in Microsoft Project Without Losing Historical Variance
In this blog post, I’m going to show you how to perform Rolling Wave Planning in Microsoft Project without corrupting your historical baseline or losing schedule variance. On long or complex projects, you rarely know every single detail task for Phase 3 and Phase 4 on Day 1, for example. Instead, you plan Phase 1…
-
Baselines, Variance & Progress Tracking, Microsoft Project (All Articles), Microsoft Project Professional
·
How to Cancel Unneeded Tasks in Microsoft Project Standard
Don’t have the Inactivate button in Microsoft Project Standard? Learn MVP Dale Howard’s step-by-step process to cancel baselined tasks without variance errors.
-
Microsoft Project (All Articles), Microsoft Project Professional, Reports, Timelines, Excel & Printing
·
How to Import Excel Projects into Microsoft Project
Importing Excel into Microsoft Project flattens your WBS by default. Learn MVP Dale Howard’s Outline Level trick plus post-import cleanup steps that work.
-
Microsoft Project (All Articles), Microsoft Project Professional, Reports, Timelines, Excel & Printing
·
How to Export Microsoft Project to Excel
Need to share your MS Project schedule in Excel? Learn MVP Dale Howard’s step-by-step Export Map workflow plus 4 Excel cleanup tricks for client reports.
-
Microsoft Project (All Articles), Microsoft Project Professional, Views, Tables, Filters & Formatting
·
How to Create a 2-Week Lookahead Filter in Microsoft Project
Need a 2-week lookahead schedule in MS Project? Learn MVP Dale Howard’s two methods: a dynamic ProjDateAdd custom filter and a built-in Status Date trick.