Last Modified:
Are your project schedules cluttered? Does it make it hard to focus on key phases? Would you like to hide tasks in Microsoft Project when you need to show just the Development and Testing tasks to stakeholders – without deleting (or restoring) anything else?
In this article, I’ll show you my favorite trick to hide tasks in your Microsoft Project using the built-in “Marked” column: a simple filter that hides tasks temporarily. It’s saved me hours in client meetings and still works flawlessly in Microsoft Project through Microsoft 365 (updated and tested December 2025).
Follow these 7 quick steps below or click here to watch the 2-minute video on my Youtube channel or click the image below.
Companion Articles in This Views, Tables, Filters & Formatting Series: Explore these connected tutorials in the same topic area to build your skills step by step:
- Current Article (You Are Here): Hide Tasks in Microsoft Project (No Deleting)
- Companion Tutorial: Remove Resource Names from Gantt Chart in Microsoft Project
- Companion Tutorial: How to Hide Summary Tasks and Outline Numbers in Microsoft Project
- Companion Tutorial: How to Add and Remove Columns in Microsoft Project
- Full Topic Hub: Browse All Views, Tables & Formatting Tutorials →
At a Glance: Hide Tasks in Microsoft Project (No Deleting):
- Applies to: Microsoft Project Standard and Professional (2016, 2019, 2021, 2024, and subscription editions).
- Key Step / Takeaway 1: Hide Tasks in Microsoft Project: Understand the Purpose
- Key Step / Takeaway 2: Step-by-Step: Hide Tasks Using the Marked Column
- Key Step / Takeaway 3: Want more tips? Here's the Latest Posts
- Best Practice: Follow the numbered step-by-step instructions below to apply this technique cleanly in your schedule.
Hide Tasks in Microsoft Project: Understand the Purpose
Imagine you have an important meeting with project stakeholders, and you only want to show them tasks from the Development and Testing section of your project. You will need to hide all other tasks to make the presentation more focused.
Step-by-Step: Hide Tasks Using the Marked Column
- Open your project in Microsoft Project (desktop version).
- Insert the Marked column
Right-click any column header (e.g., Duration) → Insert Column → type “Marked” → select Marked → OK. - Mark the tasks you want to KEEP visible
In the new Marked column, change the cells from “No” to Yes for every task you want to show.
(Tip: You can drag-fill or multi-select rows, then type “Yes” once.) - Apply the filter
Click the dropdown arrow in the Marked column header → uncheck (No) → leave only (Yes) checked → OK.
Only your marked tasks remain visible. - (Optional) Hide the Marked column
Right-click the Marked column header → Hide Column for a completely clean look. - To show everything again
Just press F3 (or View tab → Filter → No Filter).
That’s literally it. No tasks are deleted, nothing is changed permanently, and the filter travels with the file.
This little trick can be a real time-saver when you’re preparing for presentations or meetings. I hope you found this blog post article helpful. If you did, consider subscribing to my YouTube channel for more useful tips and tricks. Don’t forget to hit the notification bell to stay updated on new content. If you have any questions or comments, feel free to share them in the Comment section below. Thanks for reading!
Frequently Asked Questions
Does this hide subtasks too?
Yes – if you mark the parent task “Yes,” subtasks hide with it. For granular control, mark them individually.
How do I unhide everything?
Just press F3 (Clear Filter) or go to View > Filter > No Filter. All tasks reappear instantly.
Will this work in Microsoft Planner or Planner?
The Marked filter is desktop-only (Project 2016+). For web versions, use Groups or export to Excel for filtering.
Alternative: Hide via Outline Levels?
For summary tasks, collapse with the +/- icons (View > Outline > All Subtasks). But Marked is better for non-hierarchical hiding.
Want more tips? Here’s the Latest Posts
-
Microsoft Project (All Articles), Microsoft Project Professional, Tasks, Dependencies & Critical Path, Views, Tables, Filters & Formatting
·
How to View a Driving Dependency in Microsoft Project
In this blog post article, learn how to use the Task Path feature to display View a Driving Dependency. This includes Predecessors and Successors.
-
Microsoft Project (All Articles), Microsoft Project Professional, Tasks, Dependencies & Critical Path, Views, Tables, Filters & Formatting
·
Custom Filter to Find eDays
Learn how to create a Custom Filter to Find eDays, also known as elapsed days or calendar days.
-
Calendars, Holidays & Working Time, Microsoft Project (All Articles), Microsoft Project Professional
·
Force a Task to Start on a Specific Day of the Month
Learn how to Force a Task to Start on a Specific Day of the Month in Microsoft Project.
-
Microsoft Project (All Articles), Microsoft Project Online, Microsoft Project Professional, Microsoft Project Server
·
Force Check In Stuck Projects – 3 Methods
Force check in stuck projects in Project Server using 3 proven methods. Unblock locked files fast and restore access today.
-
Microsoft Project (All Articles), Microsoft Project Online, Microsoft Project Professional, Microsoft Project Server
·
Fix Your Enterprise Global File
If you are an application administrator for your organization’s Project Online or Project Server instance, then this blog post article will teach you how to recognize and Fix Your Enterprise Global File.
-
Baselines, Variance & Progress Tracking, Microsoft Project (All Articles), Microsoft Project Professional, Resources, Assignments & Cost Management
·
How to Calculate Percent Variance in Microsoft Project (Duration, Cost & Work Formulas)
Learn how to calculate percent variance in Microsoft Project for Duration, Cost, and Work using a custom Number field, an error-proof IIf formula, and Graphical Indicators.
-
Baselines, Variance & Progress Tracking, Microsoft Project (All Articles), Microsoft Project Professional
·
Finding Tasks Ahead of Schedule in Microsoft Project
In this blog post article, you will learn two clever tricks that will help you with Finding Tasks Ahead of Schedule.
-
Microsoft Project (All Articles), Microsoft Project Online, Microsoft Project Professional, Microsoft Project Server
·
Set Special Permissions for an Enterprise Project
Learn how to grant special permissions to another project manager in Project Online or Project Server. Follow these steps to easily accomplish the task.
-
Calendars, Holidays & Working Time, Microsoft Project (All Articles), Microsoft Project Online, Microsoft Project Professional, Microsoft Project Server
·
Edit the Enterprise Standard Calendar – How-To
Learn how to edit the Enterprise Standard Calendar in Project Server or Project Online. Step-by-step guide from an MVP expert.














Leave a Reply